Project overview
![Suspended platform over the Fernández Casado cable-stayed bridge 14 separador magenta](/wp-content/uploads/2019/07/separador_magenta.png)
![Suspended platform over the Fernández Casado cable-stayed bridge 20 uno](/wp-content/uploads/2019/07/uno.jpg)
Background
![Suspended platform over the Fernández Casado cable-stayed bridge 14 separador magenta](/wp-content/uploads/2019/07/separador_magenta.png)
The customer has to access the Fernandez Casado cable-stayed bridge strands formed by 2 piers of 120 meters high and 220 strands that support the bridge.
![Suspended platform over the Fernández Casado cable-stayed bridge 22 dos](/wp-content/uploads/2019/07/dos.jpg)
Project
![Suspended platform over the Fernández Casado cable-stayed bridge 14 separador magenta](/wp-content/uploads/2019/07/separador_magenta.png)
Development of a suspended platform to access the bridge piers’ strands along their entire length. An upper traction trolley and two suspended cradles will be used: one on each side of the strand.
![Suspended platform over the Fernández Casado cable-stayed bridge 24 tres](/wp-content/uploads/2019/07/tres.jpg)
Solution
![Suspended platform over the Fernández Casado cable-stayed bridge 14 separador magenta](/wp-content/uploads/2019/07/separador_magenta.png)
A cable anchored to the pier’s top and stretched to the bridge’s bottom is used to pull a trolley up the strand. Two special suspended platforms designed to fit this particular case are suspended from this trolley and allow workers to check and repair damage to the cable-stayed bridge’s strands.