Project overview
Background
The customer needs to access cofferdam installations and do mainteinance a dam’s inclined surface—this dam is located in the Nile River, at a hydroelectric power plant in Bujagali, Uganda.
Project
Design, manufacture, and provision of a suspended platform to access hydroelectric dam’s façade, that could go over the dam’s entire spillway surface.
Solution
A dam scaffolding to maintenance and rehabilitation. Accesus KOMPLET suspended platform equipped with 45º inclined stirrups and special wheels. The platform is suspended from plates fixed to the concrete at the top of the spillway by chemical anchors.
A removable suspended platform adapted to the diameter allows quick and safe positioning of people.